CHIMNEY DESIGN AND CONSTRUCTION

C = Construction Only
D = Design Only
J = Jumpform
P = Piles + Pile Cap
R = Raft
S = Slipform
T = Turnkey ( Design + Construction )

Previous page
CLIENT AND PROJECT
HEIGHT (m)
CONTRACT
FOUNDATION TYPE
R.C. WINDSHIELD CONTRUCTION METHOD
OPERATION TEMPERATURE DEG C
FLUE TYPE/NUMBER/DIAMETER
CONTRACT PERIOD
Japan Gas Corporation Shell Refinery Malaysia 100
T
P
S
350
Refractory brick lined
1x3.0M dia
June 98 - June 99
Formosa Chemical & Fibre Corp Cogen Stack 150
T
P
S
50-130
ASTM A36 + 1.6mm C276 Wallpaper Lining
3x3.3M
Nov 98 - Nov 99
Formosa Heavy Corporation CFB Cogen Stack 150
T
P
S
50-130
ASTM A36 + 1.6mm C276 Wallpaper lining
2x3.3M
Oct 98 - Nov 2000
Stone and Webster Lungmen Nuclear Power Station Vent Stack 150
D
P
-
-
special

2002 -2004
Formosa Chemicals & Fibre Corp
    3.5M diameter MP-6 SS317L liner
150
Liner only
-
-
60
SS317L Liner
1x3.5M

Aug 01 - Jun 02
Formosa Chemicals & Fibre Corp
                          HP-4 Stack
150
T
P
S
50-60
SS317L
1x3.6M

11 Oct 01 - 22 Nov 02
Formosa Heavy Industries
                          Hwa Ya Stack
100
T
P
S
60
A36 + C276
2x3.1M

Nov 02 - June 04
Honk Kong Electric Paul Y Lamma Liner 100
D
-
-
90-140
A36
6.0M

July 2004
Formosa Chemicals & Fibre Corp
                          HP-5 Stack
150
T
-
-
50-60
SS317L
1x3.6M

Aug 04 - Aug 05
Hwa Yang Electric Power Corp Xiamen PRC
                          CP-7
210
T
P
S
40
Q235+ ASTM B265
Gr2(Ti)
Oct 04 -July 06

Formosa Petrochemical Corporation-Mailiao,
SRU 4

110
T
P
S
316
ASTM A516 gr 60
1 x 2.1m liner
July 05 -July 06

Previous Page